CHALLENGE

Vessel Name
Challenge
Project – Construction
NB534
Vessel Type
Pelagic trawler
Area
Civil
Year
2004
Shipyard
Zamakona
Completed Works

Complete Engineering
Installation
Design, manufacturing and supply of main switchboards
Design, manufacturing and supply of alarm and PMS
Design, manufacturing and supply of engine consoles
Design, manufacturing and supply of bridge consoles
Quality Control
Commissioning and delivery
Equipment supply:

  • Cable tray
  • Cables
  • Typhoon
  • Indication and control of fire doors
  • Alarm column
  • CCTV
  • Transformers
  • Batteries and battery chargers
  • UPS
  • Navigation lights
  • Lighting
  • Fire detection and general alarm
  • Loudspeaking
  • Automatic telephones
  • Self-powered telephones
  • Outside call
  • Talk-back
  • Computer network
  • Electrical clocks